Project Name and
Location
Ogden
Grain Handling
Facility
2727 Pennsylvania
Avenue
Ogden, UT
•
Owner Name and
Address
Ogden
Grain Handling
Facility
2727 Pennsylvania
Avenue
Ogden, UT
•
General Project
Description
EPD
was subcontracted by
Terracon Consulting
Engineers &
Scientists, Inc. to
conduct continuous
core soil sampling,
groundwater sampling
and prepack
groundwater
monitoring well
installations at the
above referenced
facility
The project included
the following
activities:
1. Install eight prepack groundwater monitoring wells.
2. Conduct ten dual-tube continuous-core direct push soil borings.
3. Conduct groundwater sampling using a hydropunch retractable sampler.
The final contract
value was $67,500.
•
Miscellaneous
Comments
EPD’s
flexibility and
commitment to this
project allowed the
entire contract to
be completed within
the original
schedule and
provided additional
scopes of work for
Terracon Consulting
Engineers &
Scientists, Inc.
Next project >> |